What is used to show all activities required for project completion?

Study for the Alaska Residential Contractor Endorsement Test. Prepare with flashcards and multiple choice questions, each question includes hints and explanations. Ace your exam!

The work breakdown structure (WBS) is a fundamental project management tool used to break down a project into smaller, more manageable components. It visually displays all the tasks and activities required for project completion, organized in a hierarchical structure. By decomposing the project into detailed tasks, a WBS helps project managers and teams understand the scope of the work involved, facilitate planning and scheduling, allocate resources efficiently, and track progress throughout the project lifecycle.

In contrast, a project timeline typically outlines the schedule for tasks but does not provide the detailed breakdown of activities. A flowchart represents a process or workflow, illustrating steps and decisions but not necessarily in the hierarchical format that shows all project activities. A Gantt chart is useful for visualizing a project schedule and tracking progress over time, but it does not provide the comprehensive breakdown of all tasks that a WBS does. Therefore, the work breakdown structure is the correct choice for showing all activities needed for project completion.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy